Metro officials to convince people to shift religious structures Hyderabad, May 3 (INN): HMR MD NVS Reddy on Tuesday said that efforts are on to convince residents between Nagole and Mettuguda to shift the three religious structures to make way for the Hyderabad Metro Rail.
Speaking to media persons after officials of GHMC, Hyderabad and Cyberabad Traffic police, Hyderabad Metropolitan Water Supply and Sewerage Board, APCPDCL, BSNL, APSRTC inspected the site of the proposed Hyderabad Metro Rail between Nagole to Mettuguda, Mr Reddy said that there are three religious structures and four traffic junctions on the eight kilometer stretch.
He said that the traffic junctions would be developed while the religious structures shifted by taking the people into confidence. He also said that it is decided to lay a parallel sub road from Tarnaka to Uppal.
Apart from this, the technical issues to be sorted out included the 33KV and 11KV electricity high tension wires running along the stretch. These high tension wires will be shifted, Mr Reddy said.
The HMR MD revealed that there are about 1550 private properties on the three corridors covering a stretch of 71.16 kilometer in the city. About 150 of these properties will be acquired for the project immediately while the rest of the properties will be acquired within the next five years, Mr Reddy pointed out. He added that land recovered from Nagole to Mettuguda, Miyapur to Ameerpet will be immediately handed over to the L and T.
The HMR will have to find a solution to the opposition raised by the traders at Sultan Bazaar and Badichowdi who are unwilling to vacate their business establishments for the Metro Rail, Mr Reddy said. He said that on this half a kilometer stretch, the property owners have agreed to part with their properties but the traders are not willing.
Mr Reddy said that 200 coaches of with international standard will be imported and added that negotiations are on with 12 international companies.
The HMR MD added that the 65 kilometer project, which should have normally taken about seven and half year to be completed, will be completed within 5 years in the city. This will be due to the experience the company has gained in the past, said Mr Reddy.
News Posted: 3 May, 2011
|